Burnt Store Road Widening Project

Project Summary

The Lee County Department of Transportation and their contractor, has begun construction to widen Burnt Store Road from Diplomat Parkway to south of Tropicana Parkway to four lanes. 


The project consists of three segments: North, Middle, and South. The North Segment was completed in January 2018, and Burnt Store Road from Van Buren Parkway to Diplomat Parkway was widened to a four-lane highway. The Middle Segment will cover Diplomat Parkway to south of Tropicana Parkway and the South Segment will be from south of Tropicana Parkway to Pine Island Road.


PHASE ONE COMPLETION TIMING

North Segment:
Completed January 2018

Middle Segment:
Estimated completion Spring 2020

South Segment:
Estimated completion Fall 2023


ESTIMATED BUDGET

North Segment:
Roadwork = $15.3 million
Utility Conduits = $550,000

Middle Segment:
Roadwork = $6.7 million
Utility Conduits = $550,000

South Segment:
Roadwork = $8.7 million